WisDOT’s plan for I-94 includes a possible new interchange where Milwaukee Street would cross the freeway. Most of us would get a quicker way on. The homes closest to the ramps would get the traffic and noise that come with them. It moves ahead only if Madison and the state agree on who pays.
The plan
Milwaukee Street now ends near East Hill Parkway. WisDOT’s concept carries it over I-94 toward Gaston Road, with a roundabout on each side and ramps onto the interstate.

In short
- Corridor plan
- Decided
- WisDOT chose the overall plan in Dec 2024.
ConfirmedWisDOT decision, opens in a new tab- Who pays for the ramps
- Pending
- The City and State have not yet agreed on who pays.
- Latest public meeting
- Nov 10
- Held online
Who it affects
Most of us would gain a shortcut. Drivers heading east on I-94 could exit at Milwaukee Street instead of detouring through Highway 30 and Stoughton Road, as the district alder has noted, opens in a new tab. Nobody has published minutes saved, so treat it as likely, not promised.
Homes near the ramps would carry the cost. Around Littlemore Drive, Reston Heights and the ramps themselves, a new interchange could mean more traffic, noise, headlights and exhaust, and a busier street to cross on foot. Those are possible effects, not measured ones.
A noise wall is proposed along eastbound I-94 near the ramps. It’s built only if a majority of the votes cast by the owners and residents it would benefit say yes. Wall map and vote rules, opens in a new tab.
What’s next
Where things stand
Dec 5, 2024
Corridor plan decided
DoneWisDOT’s environmental review settled the corridor’s direction.
2025–2027 state budget
Corridor funding approved
DoneCovers the wider corridor, not these ramps.
Tue, Nov 10, 2026
Online public meeting
DoneWisDOT shared updates and its planned schedule.
Not scheduled
Madison and WisDOT agree on cost
DependsNo deal, no ramps.
2040s
Design, land and construction
LaterOnly if the deal happens. No opening date has been promised.
Will Madison and WisDOT agree on how to split the cost?
Goes ahead: If they agree
The ramps move into final design, land purchases and contracts, still years before construction.
Doesn’t go ahead: If they don’t
The interchange doesn’t go ahead as planned, because WisDOT’s concept depends on the deal.
What about the money?
No current price for the ramps has been published, and we found no approved household tax or charge. Two numbers you may hear aren’t it: $10 million was the City’s earlier local share, since removed from its 2029 plans, opens in a new tab, and $8.6 million is for a different interchange at Hoepker Road, opens in a new tab. Worth asking how the local share would be paid: borrowing, assessments, opens in a new tab on nearby property, or fees on new development, opens in a new tab.
How to have a say
WisDOT held its online meeting on Tuesday, Nov 10. WisDOT has not listed a next meeting. Meeting materials, opens in a new tab.
Step 1: Email WisDOT’s project team
Ask about the schedule and the money, or raise crossings, traffic and lighting on your street: 399094Project@dot.wi.gov.
Step 2: Follow the cost deal at City Hall
It goes through the City budget and Common Council. Ask your alder when it’s on the agenda.
Step 3: Vote on the noise wall if you’re eligible
Eligible owners and residents get a mailed ballot during final design.
Checked November 12, 2026 against the linked sources. Written with AI help; Sprecher East is an unofficial site.